|
Navy Cancels Construction of 3rd Littoral Combat Ship |
|||||
|
The Secretary of the Navy Donald C. Winter announced yesterday (April 12, 2007) terminated the construction of the third Littoral Combat Ship (LCS 3), after the Department of the Navy and Lockheed Martin (NYSE: LMT) failed to reach an agreement on the terms of a modified contract after the Navy realized that the cost of the first Lockheed ship would cost up to $375 million, far above the initial projection of $220 million. “LCS continues to be a critical warfighting requirement for our Navy to maintain dominance in the littorals and strategic choke points around the world,” said Winter. “While this is a difficult decision, we recognize that active oversight and strict cost controls in the early years are necessary to ensuring we can deliver these ships to the fleet over the long term.”
|
|
||||
|
|
||||||
|
The first and third LCS ships, constructed
by Lockheed Martin under a cost-plus contract experienced significant
cost overruns which led the Navy to stop the construction of the first
LCS 3 in January 2007. The construction of the LCS-1 (USS Freedom) is
currently underway at Lockheed Martin. Construction of two additional
vessels, LCS-2 (USS Independence)
and LCS-4 is underway at General Dynamics. The Navy announced it will
closely monitor their cost performance at General Dynamics', to prevent
the repetition of such problems. "General Dynamics’ ships will
continue on a cost-plus basis as long as its costs remain defined and
manageable. If the cost performance becomes unacceptable, then General
Dynamics will be subject to similar restructuring requirements."
Resulting from these problems, the Navy plans to transition to a single
seaframe configuration in fiscal year 2010, following an operational assessment. Stevens admitted that while Lockheed Martin maintained the ship's schedule
and improved on its design, cost overruns have occurred. The company responded
to the Navy's request to restructure the contact for the second LCS ship
but failed to reach an agreement. "We believe that our proposal was
fully consistent with the Secretary's stated desire to bring the benefits
of increased competition to shipbuilding while holding the Navy's industrial
partners accountable for cost performance within their control".
"Our team is understandably frustrated that, having invested nearly
three years of dedicated effort and significant corporate resources to
bring LCS 1 to within 20 percent of completion, we will not have the opportunity
to apply lessons learned to a second ship" |
||||||
| |
||||||